Cushman Dam No. 1 is a hydroelectric dam on the North Fork of the Skokomish River in Mason County, Washington, which in derogation of the natural and treaty rights of the Native inhabitants impounded and enlarged the formerly natural Lake Cushman, leading to damage claims in excess of $5 billion and an eventual settlement agreement with the Skokomish tribe that terminates the right to operate the dam(s) after 2048.Template:Citation needed It was built by Tacoma City Light (now Tacoma Power) in 1924–1926. Tacoma's demand for electricity grew rapidly after World War I. Tacoma City Light's Nisqually River Hydroelectric Project, built in 1912, could not meet the demand and the utility decided to build a new hydroelectric project on the North Fork Skokomish River. The dam and powerhouse first began to deliver electricity on March 23, 1926.<ref name=historylink>{{#invoke:citation/CS1|citation |CitationClass=web }}</ref><ref name=TAC032426>"First Unit of Cushman Is in Service", The Tacoma (WA) Daily Ledger, March 24, 1926, p.1</ref>

It has a concrete arch design and includes 90,000 cubic yards (69,000 m³) of concrete, covering a whole Template:Convert of water. Two 21,600 kilowatt generators provide 127 million kilowatt-hours annually to the Tacoma Power system.

Construction began on July 7, 1924, under the commissioner Ira S. Davisson. It has a top width of Template:Convert and a base width of Template:Convert, at Template:Convert high and Template:Convert long. The transmission of electricity to Tacoma, over lines crossing Tacoma Narrows, was dedicated on May 24, 1926 with the push of a button by President Calvin Coolidge in a ceremony at the White House. Although there was a fanciful claim by Davisson later that U.S. President Coolidge "touched the key" that "sent current pulsing from Washington, D.C. into the Olympic Mountains and set the huge turbines whirring,",<ref name=historylink/> the current generated was not sent from Washington, D.C., and plant was in operation for two months before President Coolidge (on May 24) pressed a "special key" button at the White House to signal the official opening and celebration.<ref>"Tacoma Opens New Unit at Lake Cushman", Seattle Union Record, May 25, 1926, p.1</ref> The generation of electricity on March 23, 1926, had been started "without ceremony or celebration" and residents of Tacoma were "unaware that the generation of power from the Cushman project had been realized".<ref>"Cushman Wheels Turn and 'Juice" Is Made"— Tacomans, Without Known It, Use Electricity From Their Brand New Plant", Tacoma (WA) News Tribune, March 24, 1926, p.1</ref> A contemporary account noted that Davisson and superintendent Alvin F. Darland "threw the switches and made the connections which sent the mighty pulsations of electrical power speeding over the cables of the 42-mile transmission line into Tacoma."<ref name=TAC032426/> A second, smaller dam, Cushman Dam No. 2, Template:Convert downstream of Dam No. 1, was completed by December 1930.<ref>{{#invoke:citation/CS1|citation |CitationClass=web }}</ref>

See also

Template:Stack

References

Template:Reflist

Template:National Register of Historic Places