EastLink (Melbourne)

From Vero - Wikipedia
Jump to navigation Jump to search

Template:Short description Template:Distinguish Template:Use Australian English Template:Use dmy dates Template:Infobox Australian road

EastLink is a tolled section of the M3 freeway linking a large area through the eastern and south-eastern suburbs of Melbourne, Australia.<ref name='SEITA - About Eastlink'>Template:Cite web</ref>

EastLink is electronically tolled with no cash booths, using a system developed by SICE. The SICE Tolling System is similar to (and interoperable with) the e-TAG system used on the CityLink tollway. EastLink was opened to traffic on Sunday 29 June 2008 and in conjunction with the opening, a month-long toll-free period occurred before regular tolling commenced on 27 July 2008.<ref name='EastLink News - Opening'>Template:Cite web</ref>

The project was constructed by a joint venture of Australian construction companies Thiess Contractors and John Holland,<ref name='SEITA - Whos Involved'>Template:Cite web</ref> with tolling system contracted to SICE, and mechanical and electrical work contracted to United Group Infrastructure.<ref>Template:Cite web</ref> The final project cost was A$2.5 billion.

Signs at the entrances and on the tollway direct to Ringwood, Dandenong, Frankston and Doncaster.

History

File:EastLink Boronia Road.jpg
Construction of EastLink over Boronia Road in Wantirna
File:EastLink looking south from the Oakwood Avenue bridge - panoramio.jpg
Eastlink in December 2009

The road was originally shown in the 1969 Melbourne Transportation Plan as the F35 Freeway.

The freeway has been a contentious issue, amid concerns over environmental damage and the possibility it would lead to a 'complete' metropolitan ring road. In October 1999, the incoming Bracks Government announced that the freeway (which Labor had not promised at the election) had been scrapped. Instead the government promised to investigate a preferred route for the Rowville railway line and extend tram route 75 to Knox, neither of which have eventuated.<ref name="The Age - Freeway Link Scrapped">Template:Cite news</ref> However, in a "major policy about-face", the Bracks Government announced in August 2000 that it would seek federal funding for the freeway.<ref name="The Age - Scoresby Freeway Back On Agenda">Template:Cite news</ref> To obtain funding, the freeway would need to be classified as a road of "national importance", despite the fact that it did not form part of the national highway system. The "U-turn"' on the freeway was strongly criticised by opponents such as the Public Transport Users Association, because it would result in proposed public transport alternatives, such as the Rowville railway line, being scrapped.<ref name="The Age - Anger At U-turn On Scoresby Freeway">Template:Cite news</ref>

In 2001, University of Melbourne academic Paul Mees launched legal action in the Federal Court seeking an injunction, under section 475 of the Environment Protection and Biodiversity Conservation Act 1999, to prevent Transport Minister Peter Batchelor and the Roads Corporation (VicRoads) from "taking any further action relating to the construction of the Scoresby freeway or the Eastern Ring Road". He alleged that the freeway would threaten migratory birds, plant species and wetlands and that the freeway was part of a larger plan to build a metropolitan ring road to Greensborough.<ref name="The Age - Scoresby Freeway Faces Hurdle">Template:Cite news</ref> In light of the court case, state government bureaucrats removed references to the metropolitan ring road from a draft Metropolitan Strategy.<ref name="The Age - Ring road plan altered before case">Template:Cite news</ref>

In 2003, the Southern and Eastern Integrated Transport Authority (SEITA) was established by the Victorian Government, to manage and oversee the project on behalf of the government. SEITA was responsible for managing the process of selecting a private sector bidder.<ref name='SEITA - Whos Involved' />

In October 2004, SEITA awarded the contract for the design, construction, and operation of EastLink to ConnectEast, a company that was publicly listed on the ASX in November 2004. ConnectEast subsequently contracted Thiess John Holland, a group formed by the partnership of two major construction companies, to carry out the detailed design and construction of EastLink.<ref name='SEITA - Whos Involved' />

ConnectEast, as owner of the road, is responsible for its day-to-day management until the concession deed expires in 2043. EastLink's construction began in March 2005, and the road opened on 29 June 2008.

The opening of the road on 29 June 2008 saw traffic on nearby Stud, Springvale and Blackburn Roads drop by 30% to 40%,<ref>Template:Cite news</ref> but traffic on the Eastern Freeway rose by 5 per cent at the Burke Road intersection, and by about 1–2 per cent at Hoddle Street in the city.<ref>Template:Cite news</ref> On average 270,868 cars, trucks and motorbikes travelled on the road every day until the tolling was introduced on 23 July.<ref name=takeatoll>Template:Cite news</ref> In the first week after the introduction of tolls, the average number of daily trips fell to 133,722. This was in line with estimates of a 40 to 50 per cent decline, but is a third below prospectus forecasts. The average toll per trip was $3.10 – above the estimate of $2.91.<ref name=takeatoll />

In its first six months of operation, Eastlink made a loss of almost $93 million.<ref name="Eastlink revenue loss">Template:Cite news</ref> In 2010, the road had to be refinanced, with its traffic forecasts rewritten due to lower than expected traffic volumes.<ref name="ABC - Eastlink forecasts rewritten">Template:Cite news</ref>

The tollway was closed for the first time on 18 February 2010 when a semi-trailer crashed into a large pylon holding up a road sign gantry. The driver had lost control on the north-bound side of the tollway, 300m from the Wellington Rd exit, and was killed in the accident.

Naming history

Over the years the project was variously referred to as the Eastern Ring Road, Scoresby Freeway, Scoresby Bypass, and Mitcham-Frankston Freeway.

On 23 March 2005, with the beginning of construction on the project, then Premier Steve Bracks announced that the road would be called EastLink, at a ceremony in Rowville.<ref name="Silkstone 10">Template:Cite news</ref> The new name was reportedly chosen because it was easier to say, apparently easier to remember, and would fit on street directories.

On 27 February 2008, it was announced that the EastLink / Monash Freeway interchange would be named the "Tom Wills Interchange", after the founder of Australian rules football Tom Wills.<ref name="seita.com.au">EastLink interchange honours one of football's founders Template:Webarchive SEITA. 27 February 2008. Retrieved 26 March 2008.</ref> On 24 March 2008, Roads Minister Tim Pallas announced that the twin tunnels would be named "Melba" and "Mullum Mullum", in the inbound and outbound direction respectively.<ref name="news.com.au">Template:Cite news</ref>

Route

File:Eastlink first day open.jpg
Maroondah Highway bridge, Ringwood looking towards the railway bridge
File:EastLink looking south from Koomba Road bridge.jpg
EastLink looking south from the Koomba Road footbridge before opening.
File:EastLink Operations Centre.jpg
The EastLink Operations Centre in Ringwood during construction.
File:Eastlink overpass.JPG
Night-shot of overpass spanning Eastlink, near the Burwood Rd exit.

EastLink begins at the eastern end of the Eastern Freeway at Springvale Road in Nunawading, before tunnelling eastward towards Ringwood under the Mullum Mullum Creek area. It then travels 40 km south towards Frankston, passing through the suburbs of Wantirna, Wantirna South, Scoresby, Rowville, Mulgrave, Dandenong North, Noble Park, Keysborough, Dandenong South, Bangholme, and Carrum Downs, before ending at the northern end of the Frankston Freeway.<ref name='EastLink - Melway Route'>Template:Cite web</ref> The majority of the freeway has three lanes running in each direction, while between Thompson Rd and Frankston Freeway, there are 2 lanes running in each direction.<ref name='SEITA - EastLink F&F'>Template:Cite web</ref>

The standard travel time on EastLink in both directions, is 26 minutes, (12 minutes between Frankston Freeway / Peninsula Link and the Monash Freeway, 7 minutes between the Monash Freeway and the Burwood Highway and 7 minutes between the Burwood Highway and Springvale Road). Typical travel time is between 30 and 40 minutes.

EastLink does not regularly have peak period congestion like other urban metropolitan freeways in Melbourne. However, delays can be experienced following roadworks or they might be residual, following an incident. Occasionally, traffic congestion occurs between Thompsons Road and the junction with the other three freeways in Carrum Downs, where the freeway changes from three to two lanes. If the congestion builds, the travel time can reach 40 minutes or beyond.

While the construction of Eastlink alleviated congestion on Springvale Road, it has had the effect of funnelling the traffic onto other roads, particularly increasing traffic on the Eastern Freeway.


Exits and interchanges

Template:AUSinttop Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:VICint Template:Jctbtm

Dandenong Bypass

Template:Main A 4.8 km section of the Dingley Freeway called the Dandenong Bypass (also referred to as the Dandenong Southern Bypass during its construction) was built by ConnectEast and Thiess John Holland as part of the EastLink project.<ref name='SEITA - Dandenong Bypass'>Template:Cite web</ref> The bypass opened on 9 December 2007.<ref>EastLink tollway to open six months early Herald Sun 10 December 2007. Retrieved 12 December 2007.</ref>

Tolling

File:Eastlink tunnels Ringwood portal.jpg
Ringwood portal of the tunnels under the Mullum Mullum Valley
File:Hillcrest Reserve and the Eastlink Melba Tunnel.jpg
Hillcrest Reserve and the Eastlink Melba Tunnel in January 2020

EastLink is electronically tolled via a system commercially called Breeze, entirely provided by SICE, Spanish system integrator company with broad experience in the tolling market. This system is fully interoperable with all other tollways in Australia, including the Transurban e-TAG system used on CityLink.<ref name='Breeze - Products'>Template:Cite web</ref>

The system features a uniquely designed electronic vehicle tag, the "Breeze Tag", which is about half the size of the standard design of e-TAG. The Breeze system is provided by Spanish company SICE,<ref name='SICE - EastLink'>Template:Cite web</ref> with the Road Side Equipment, including the Breeze Tags, provided by Swedish firm Kapsch TrafficCom AB, under the PREMID brand of DSRC products.<ref name='Kapsch'>Template:Cite web</ref>

Tolls on EastLink can be charged in three different ways:

  • By having any Australian electronic tolling "tag" (such as a Breeze Tag, or Transurban's e-TAG) in the vehicle. Tolls are charged to the corresponding tag account.<ref name='Breeze - tag account'>Template:Cite web</ref>
  • By registering a Breeze non-tag account with ConnectEast. A photograph of the number plate(s) of each vehicle is taken and matched to an account, charging the account holder the toll plus a small processing fee (30c, waived for motorcycles). Alternatively, "Access" accounts registered with CityLink may also be used in this manner.<ref name='Breeze - non-tag account'>Template:Cite web</ref> Vehicles with metalised windscreens which cannot be electronically scanned will avoid the extra fee if the owner registers it with Eastlink as such. The toll is then charged to the account by number plate recognition.
  • By purchasing a "trip pass" valid for a single one-way trip on EastLink from ConnectEast either over the telephone, via the EastLink website, or from a retail outlet. Vehicle recognition for trip passes is done the same way as for non-tag accounts. Drivers can purchase multiple trip passes at once, as passes are stored until used. However, trip passes expire six months from the date of purchase.<ref name='Breeze - trip pass'>Template:Cite web</ref>

If a driver travels on EastLink without taking any of the three actions above to pay for the toll(s) either prior to, or within three days after travel, an invoice for cost of the toll(s) plus an account processing fee will be sent to the registered vehicle's owner. If the toll invoice is not paid, an overdue notice (with an additional processing fee) is issued. If the invoice is still not paid, a fine is issued by Victoria Police.<ref name='Breeze - invoice'>Template:Cite web</ref>

The concession period held by ConnectEast is due to end on 30 November 2043,<ref name="DTV21AR">Template:Cite news</ref> after which the ownership of the road will be transferred to the state.

Prices and discounts

File:Melba tunnel.jpg
Inside the Melba (westbound) tunnel

Multiple toll points are located along the EastLink, with each toll point charging a fixed fee.<ref name=calculator>Template:Cite web</ref> The total toll incurred per trip is the smaller of the trip cap or the total price of toll points passed through. The exception is taxis which pay a fixed price for travel on any section south of Maroondah Highway, regardless of the distance travelled or number of toll points passed through.

The cheapest toll points are located between Maroondah Highway and High Street Road, with slightly more expensive toll points located in the longer sections near the south of the tollway, and the most expensive one within the tunnel section between Maroondah Highway / Ringwood Bypass and Springvale Road. Motorcycle prices are half of cars, while higher rates apply for larger vehicles.<ref name='EastLink - Tolls'>Template:Cite web</ref>

Discounts are also offered to car drivers. A 20 per cent discount applies to the cost of any car trip(s) taken on a Saturday or Sunday and also to one way trips between two consecutive interchanges (excluding the tunnels) on weekdays.

Template:Hatnote {{#section:Toll roads in Australia|header_vic}} {{#section:Toll roads in Australia|eastlink}} {{#section:Toll roads in Australia|footer_vic}}

Shared path

The EastLink Trail is a shared walking and cycle path that follows a similar north–south route to the EastLink project. Using it, cyclists and pedestrians are able to cycle or walk most of the distance of the road, along a 3-metre wide dedicated concrete path. Many major roads are crossed via under or over passes. Some roads, such as High Street Road (and until November 2009, Burwood Highway), require crossing the road at grade.<ref name='EastLink - Trail'>Template:Cite web</ref>

In wet weather, two underpasses are not trafficable as they have been built on floodways. These are the Ferntree Gully Road underpass and the Wellington Road underpass. After a medium amount of rain the underpasses flood and trail users must cross over the major roads to continue along the path. This can prove dangerous and during peak traffic times, trail users are known to have waited up to 20 minutes to safely cross the roads when the underpasses have flooded.

The Eastlink trail stops in Dandenong and does not continue. Users may take the Dandenong Creek Trail from this point which will take them to Carrum, where they will be able to join the Peninsula Link trail to Frankston and Mornington.

For those using the trail, substantial deviations from EastLink must be taken into account in travel times as the shared path does not follow the freeway in many cases as existing trails were joined up to the trails specifically built during the construction of the road. This has led to some very twisty sections of trail and in some cases, detours of over 3 km from the EastLink.

Template:Wide image Template:Clear

Environmental issues

File:EastLink Bridge over Dandenong Creek.jpg
Constructing the EastLink bridge over Dandenong Creek, in Ringwood/Wantirna

The road was the subject of an Environmental Effects Statement (June 1998), which was followed by a public hearing process in April 1999 before the final Government decision to proceed. The statement predicted an 18.5per cent increase in carbon dioxide, impacts on groundwater and wetlands, high impacts on areas of conservation value and the potential to affect 38 species of rare or threatened fauna and flora if the freeway was built.<ref name="The Age - Scoresby Freeway Faces Hurdle" />

EastLink's builders stated that the road would relieve traffic congestion throughout Melbourne's eastern and south-eastern suburbs, resulting in more efficient traffic flow, therefore reducing fuel consumption and exhaust output.<ref>Template:Cite book</ref>

During the planning phase (then a VicRoads project), a large debate surrounding damage to the Mullum Mullum Valley occurred. A number of options for the path of the road through the valley were considered. The option chosen – for two 1.6 km tunnels – was the second-to-most expensive, and the second-to-most environmentally friendly.<ref>Template:Cite news</ref> Other options considered in planning included a surface road for the entire length, much shorter tunnels, and slightly longer tunnels.

However, despite the attention on tunnelling beneath the Mullum Mullum Gorge, the Ringwood Interchange is entirely above-ground and has resulted in relocation of the creek through this area.